Updates:
12-08-2012: We visited (Harinath,Kishore and Divaker reddy) Dyvakrupa orphanage at secunderabad thanda for new facilities Inauguration function. We spent Rs: 3 Lakhs to provide these facilities with donors support. What it seemed was not feasible is a reality (with the required facilities like toilets, bore,gas connection with double cylinders,borewell with motor, gates, big hall etc).
Work update: Click Here
Thanks from everyone at Dyvakrupa:Click Here
photos: Click Here
03-06-2012: We got the following done so far
We have released INR 1.5L till now.
1. LPG connection
2. Ground leveling work completed (see the video below) with approx cost of Rs.90,000
3. Borewell is drilled
4. Pipeline for water supply (from an existing borewell to the site)
5. In progress:Toilets, Gate,Water tank (for storage)
Videos:Video 1
Volunteers: Harinath (President, TMAD), Kishore (Board Member, TMAD)
Donors contribution in Rupees
Donors | Amount |
Padegal Adarsh | 8000 |
Venkat | 5000 |
Bulusu Sharat Chandra | 3000 |
Naresh Samala | 5000 |
Vinay Azd | 25000 |
Anonymous | 3000 |
Praveen Dasari | 50000 |
Suresh E | 10000 |
Total | 109000 |
Donors contribution in Dollars
Donors | Amount |
Yavan Madduri | 100 |
Sravanth Poreddy | 102 |
Shilpa Vijaypuram | 200 |
Shashikanth Garlapati | 10 |
Ramesh Bevara | 20 |
Uday Nallamolu | 20 |
Nagesh Chandra | 50 |
Srinivas Motupalli | 30 |
Anil Meda | 30 |
Gouthami Nelavelli | 200 |
Sridhar Nannuru | 50 |
Venkatesh Pallepati | 50 |
Vijaya Kesari | 100 |
Soumya Pingili | 50 |
Vaddiraju Srinivas | 40 |
Skanda Pokkunuri | 100 |
Subash Sangam | 200 |
Madhuri Naikoti | 100 |
Chandrasekhar Kandimalla | 100 |
Praveena Mettu | 100 |
Preethi Vodnala | 25 |
Sharat Konatham | 50 |
Srikanth Akella | 20 |
Manoj Kasam | 100 |
Rajaram Kanaka | 20 |
Anonymous | 75 |
Jayasree Upaydhay | 50 |
Dayasagar Medaboina | 200 |
Sunder Polepaka | 100 |
Dilip Banda | 75 |
Abhishek Erabathini | 200 |
Kiran Kumar Munnanoor | 100 |
Mallikarjun Reddy Likki | 100 |
Sujith Maram | 101 |
Srikar Nimmagadda | 51 |
Sudhir Sibbineni | 101 |
Madhusudhan Reddy Kanapuram | 250 |
Satish Thota | 50 |
Amar Karimilla | 100 |
Total | 3420 |
22-04-2012:
About the Dyva krupa orphan home:
Mr. Lokesh Nayik is a BA(1998 batch) discontinued. He has been working as a contract labor or daily coolie. He saw a kid eating food along with dogs from the thrown away plate at a function. He was heartened by the plight of that boy and then he brought the kid home. With strong support from his wife (parvathi) he started taking care of more orphan kids. people around this area, when they found an orphan, then started referring them to lokesh.
Lokesh registered a society with the help and guidance of local people officer with name Ballo Banjara welfare society (reg. no 411/2008). At present he has 26 kids at that he is taking care of. They are of the age group 5 - 15, in which 11 of them are girls.He got help from donors in that area. Mr. Ramprasad DSP, Mrs Madhumathi (sponsored 31k) etc.
At present there are around 7 donors (from police department) who are contributing 500 per month. Also he gets support from local business people in terms of rice etc. He is able to manage the operational expenses.What is is really looking for is to develop the land which he bought for the orphanage purpose. He and his wife spent extra time and build 4 rooms (made of cement bricks made by he and his wife and cement sheets). As the area is on the outskirts, there are lot of snakes and scorpions around so he started building fencing around the area. He build the boundary walls with the help of donors. Now he want to clear the ground properly (it is full of rocks and uneven). It needs around 300 tractors load of soil to make it flat. Also bathrooms for kids and additional 4 rooms. Also for water facility he plans to put up a borewell and motor.
Parvathi (Lokesh Nayik wife is preparing food for the kids on typical stove with firewood. Let us help them in getting a LPG connection.All the kids treat Lokesh and his wife as their parents.
The cost details are given below.
Specific requirements are:
1. LPG Connection -> 6k ( + approx 2k for additional cylinder)
2 . Bore and pump for water? - 25K
3. Bathrooms (4) - 25k
4. Gate -> 30k
5. Ground leveling - around INR 1 Lakh
Total cost approx: INR 2Lakh
Volunteers: Harinath (President, TMAD), Kishore (Board Member, TMAD)